Pavilion Beaver D3.5m x W5m
UK Timbersolution
£4770
Oak Pavilion — Step-by-Step Installation Guide Project: Oak pavilion (example photos: heavy green oak posts, braces, ridge/truss frame) Typical crew: 4 installers Estimated install time: 2-3 days (site prep and foundation separate) Pre-installation checks preparation Confirm drawings dimensions. Verify the approved shop drawings, post positions, heights, and bolt/dowel locations. Mark post centres on site. Site foundation ready. Ensure concrete pads/piers are poured, cured and within ±5 mm level tolerance. Pads should be below frost line, reinforced, and sized for post loads. Delivery inventor